Condition | Maintenance Procedure | Inspection Comments | Inspection Date | Next Inspection Date | |
Very Good (Grade 1) | Inspection only | 06/05/2020 Clear, inspected by William Webber | 10/06/2020 | 10/12/2020 | Photos |
Poor (Grade 4) | General maintenance | 18/02/2020 Large build up of silt/gravel/rock in sump and water courses. 18/02/2020 Cleared as best as could be done in conditions | 17/03/2020 | Photos | |
Poor (Grade 4) | General maintenance | 27/02/2020 Complete dig out of sump 27/02/2020 Cleared | 17/03/2020 | Photos | |
Fair (Grade 3) | General maintenance | 16/01/2020 Build up of sticks and twigs in two water courses. 16/01/2020 Cleared. | 11/03/2020 | Photos | |
Very Poor (Grade 5) | General maintenance | Twigs Sticks in spill - way | 15/01/2020 | Photos | |
Very Good (Grade 1) | Inspection only | No Works Required | 21/11/2019 | Photos | |
Good (Grade 2) | Inspection only | no work required | 18/01/2018 | Photos | |
18/01/2018 | Photos | ||||
Good (Grade 2) | Inspection only | no works required | 04/12/2017 | Photos | |
Good (Grade 2) | Inspection only | 11/10/2017 | Photos | ||
Fair (Grade 3) | General maintenance | 10/07/2017 Quantity of sticks in sump. Weeds growing on spillway. | 06/09/2017 | Photos | |
Good (Grade 2) | Inspection only | no works required | 06/06/2017 | Photos | |
Good (Grade 2) | Inspection only | no work required | 16/02/2017 | Photos | |
Very Good (Grade 1) | Inspection only | no work required | 16/12/2016 | Photos | |
Very Good (Grade 1) | General maintenance | 18/12/2015 Rubble building - cleared | 21/09/2016 | Photos | |
Very Good (Grade 1) | Inspection only | 7/6/16 Clear | 18/09/2016 | Photos | |
Very Good (Grade 1) | Inspection only | no works required | 19/04/2016 | Photos | |
Very Poor (Grade 5) | General maintenance | works to clear watercourse of rubble above new inlet system carried out on 13 April 2016 | 14/04/2016 | Photos | |
Fair (Grade 3) | General maintenance | 09/12/2015 Large quantity of gravel and scree removed from sump to expose pipe. | 23/12/2015 | Photos | |
Very Good (Grade 1) | Inspection only | 14/11/2015 Clear | 23/12/2015 | Photos | |
Good (Grade 2) | Inspection only | no works required | 12/10/2015 | Photos | |
Good (Grade 2) | Inspection only | no works required | 13/08/2015 | Photos | |
Good (Grade 2) | Inspection only | no works required | 04/06/2015 | Photos | |
05/01/2015 | Photos | ||||
05/01/2015 | Photos | ||||
05/01/2015 | Photos | ||||
05/01/2015 | Photos | ||||
Very Good (Grade 1) | Inspection only | no works required | 05/01/2015 | Photos | |
Good (Grade 2) | Inspection only | no works required | 27/12/2014 | Photos | |
Good (Grade 2) | Inspection only | no works required | 27/12/2014 | Photos | |
Good (Grade 2) | Inspection only | clear | 30/11/2014 | Photos | |
Good (Grade 2) | Inspection only | clear | 30/11/2014 | Photos | |
Good (Grade 2) | Inspection only | clear | 30/11/2014 | Photos | |
18/08/2014 | Photos | ||||
Very Good (Grade 1) | Inspection only | no works required | 18/08/2014 | Photos | |
18/08/2014 | Photos | ||||
18/08/2014 | Photos | ||||
Very Good (Grade 1) | Inspection only | no works required | 18/07/2014 | Photos | |
Very Good (Grade 1) | Inspection only | no works required | 13/05/2014 | Photos | |
Good (Grade 2) | General maintenance | pay back team works required | 26/03/2014 | Photos | |
Very Good (Grade 1) | Inspection only | no works required | 26/03/2014 | Photos | |
Good (Grade 2) | Inspection only | no works required | 18/12/2013 | Photos | |
Fair (Grade 3) | General maintenance | manhole an sump needs cleaned | 24/10/2013 | Photos | |
Very Good (Grade 1) | Inspection only | all cleared | 24/10/2013 | Photos | |
Very Good (Grade 1) | Inspection only | no works required | 17/10/2013 | Photos | |
Good (Grade 2) | Inspection only | no works required | 05/09/2013 | Photos | |
Good (Grade 2) | Inspection only | no works | 30/04/2013 | Photos | |
Good (Grade 2) | Inspection only | clear | 12/11/2012 | Photos | |
Fair (Grade 3) | Additional work required | manhole on south side full with sediment washed in following storm of 21 august . works arranged to remove sediments for week commencing 3rd september. further note - works complete together with clearance of pipework connections 5 september. | 05/09/2012 | Photos | |
Fair (Grade 3) | General maintenance | hake clear in glen affric. lot of small stone needs cleared. did not inspect manhole. | 28/08/2012 | Photos | |
Very Good (Grade 1) | General maintenance | no work required | 13/04/2012 | Photos | |
Very Good (Grade 1) | Additional work required | gully emptier to remove silt and gravel from inspection chamber on 01.12.11 | 05/12/2011 | Photos | |
Very Good (Grade 1) | Inspection only | no work required | 13/10/2011 | Photos |